UK energy bills could rise under government plans to fund nuclear

Spread the love

https://www.politico.eu/article/energy-bills-rise-under-uk-government-plans-fund-nuclear/

A final investment for the plants is planned before the next election | Carl Court/Getty Images

LONDON The U.K. government is mulling plans which would hike household energy bills to help pay for a new nuclear energy plant.

Ministers are considering tweaking the funding deal for Sizewell C, a proposed £20 billion nuclear plant in Suffolk, as they scramble to attract investors.

Under one proposal being looked at in Whitehall, the development would be part funded by electricity suppliers — and those firms “would be expected to pass these costs onto consumers through their electricity bills,” according to a consultation paper on the plans.

The Department for Energy Security and Net Zero is set to publish its response to that consultation later this week, according to two industry figures granted anonymity to discuss the process.

Officials insist potential additional charges to consumers would be low. But any move leading to higher bills would be controversial during a cost-of-living crisis driven by two years of rising energy costs.

https://www.politico.eu/article/energy-bills-rise-under-uk-government-plans-fund-nuclear/

Continue ReadingUK energy bills could rise under government plans to fund nuclear

Spending watchdog launches investigation into Sellafield

Spread the love

https://www.theguardian.com/business/2024/feb/15/spending-watchdog-launches-investigation-into-sellafield

Sellafield is Europe’s most toxic nuclear site. Photograph: David Levene/The Guardian

Britain’s public spending watchdog has launched an investigation into risks and costs at Sellafield, the UK’s biggest nuclear waste dump.

The National Audit Office (NAO), which scrutinises the use of public funds, has announced it will examine whether the Cumbria site is managing and prioritising the risks and hazards of the site effectively as well as deploying resources appropriately and continuing to improve its project management.

The findings of its investigation are expected to be published this autumn.

Sellafield is Europe’s most toxic nuclear site and also one of the UK’s most expensive infrastructure projects, with the NAO estimating it could cost £84bn to maintain the site into the next century.

Last year, Nuclear Leaks, a Guardian investigation into activities at Sellafield revealed problems with cybersecurity, a radioactive leak and a “toxic” workplace culture at the waste dump.

Predictions of the ultimate bill for the site, which holds about 85% of the UK’s nuclear waste, vary. It cost £2.5bn to run the site last year, and the government estimates it could ultimately take £263bn to manage the country’s ageing nuclear sites, of which Sellafield accounts for the largest portion.

https://www.theguardian.com/business/2024/feb/15/spending-watchdog-launches-investigation-into-sellafield

https://onaquietday.org/category/sellafield/

Continue ReadingSpending watchdog launches investigation into Sellafield

Hinkley Point C could be delayed to 2031 and cost up to £35bn, says EDF

Spread the love

https://www.theguardian.com/business/2024/jan/23/hinkley-point-c-could-be-delayed-to-2031-and-cost-up-to-35bn-says-edf

As nuclear plant is hit by further delay, real cost will be far higher after inflation is included, as project uses 2015 prices

In 2007, the then EDF chief executive said that by Christmas in 2017, turkeys would be cooked using electricity generated from atomic power from Hinkley. Photograph: Ben Birchall/PA

The owner of Hinkley Point C has blamed inflation, Covid and Brexit as it announced the nuclear power plant project could be delayed by a further four years, and cost £2.3bn more.

The plant in Somerset, which has been under construction since 2016, is now expected to be finished by 2031 and cost up to £35bn, France’s EDF said. However, the cost will be far higher once inflation is taken into account, because EDF is using 2015 prices.

The latest in a series of setbacks represents a huge delay to the project’s initial timescale. In 2007, the then EDF chief executive Vincent de Rivaz said that by Christmas in 2017, turkeys would be cooked using electricity generated from atomic power at Hinkley. When the project was finally given the green light in 2016, its cost was estimated at £18bn.

However, the Hinkley Point C delay will add to concerns over project delays and costs, as well as skills in an industry earmarked to deliver a quarter of the national electricity demand by 2050.

https://www.theguardian.com/business/2024/jan/23/hinkley-point-c-could-be-delayed-to-2031-and-cost-up-to-35bn-says-edf

comment by dizzy: This is not at all surprising. EDF were extremely late and over-budget with 2 nuclear power station of the same design as Hinkley C when it started.

Continue ReadingHinkley Point C could be delayed to 2031 and cost up to £35bn, says EDF

Sellafield nuclear site hacked

Spread the love
A seabird staying warm in one of Sellafield nuclear dump’s open-air ponds.

https://www.theguardian.com/business/2023/dec/04/sellafield-nuclear-site-hacked-groups-russia-china

The UK’s most hazardous nuclear site, Sellafield, has been hacked into by cyber groups … the Guardian can reveal.

The astonishing disclosure and its potential effects have been consistently covered up by senior staff at the vast nuclear waste and decommissioning site, the investigation has found.

The Guardian has discovered that the authorities do not know exactly when the IT systems were first compromised. But sources said breaches were first detected as far back as 2015, when experts realised sleeper malware – software that can lurk and be used to spy or attack systems – had been embedded in Sellafield’s computer networks.

The full extent of any data loss and any ongoing risks to systems was made harder to quantify by Sellafield’s failure to alert nuclear regulators for several years, sources said.

The revelations have emerged in Nuclear Leaks, a year-long Guardian investigation into cyber hacking, radioactive contamination and toxic workplace culture at Sellafield.

The site has the largest store of plutonium on the planet and is a sprawling rubbish dump for nuclear waste from weapons programmes and decades of atomic power generation.

In one highly embarrassing incident last July, login details and passwords for secure IT systems were inadvertently broadcast on national TV by the BBC One nature series Countryfileafter crews were invited into the secure site for a piece on rural communities and the nuclear industry.

https://www.theguardian.com/business/2023/dec/04/sellafield-nuclear-site-hacked-groups-russia-china

Shitty open-air pond at Sellafield nuclear waste dump containing spent nuclear fuel rods. Notice the seabird staying warm.

https://onaquietday.org/search/Sellafield/

Sellafield: ‘bottomless pit of hell, money and despair’ at Europe’s most toxic nuclear site

Continue ReadingSellafield nuclear site hacked

Campaigners win permission to appeal against building of Sizewell C

Spread the love
3D-generated image of the Sizewell C Nuclear Power Plant Photo: Public Domain
3D-generated image of the Sizewell C Nuclear Power Plant Photo: Public Domain

https://morningstaronline.co.uk/article/b/campaigners-win-permission-appeal-against-building-sizewell-c

CAMPAIGNERS have won permission to appeal against the building of Sizewell C nuclear power station in Suffolk because the government did not ensure there was a sufficient water supply to meet its demands.

The Court of Appeal overturned a refusal by the High Court to grant a judicial review into the decision by Kwasi Kwarteng, the then-business secretary, to give the station on the Suffolk coast the go-ahead.

The case was brought by the Together Against Sizewell C (Tasc) campaign group.

Tasc’s case included an argument that because of the power station’s need for huge quantities of water for its cooling system, the development should include a desalination plant to avoid endangering local domestic water supplies.

Court of Appeal judge Lord Justice Coulson said that given that Mr Kwarteng gave permission for the power station against the advice of the planning authority, and because of Tasc’s arguments about the need for a water supply, the appeal had “a real prospect of success.”

https://morningstaronline.co.uk/article/b/campaigners-win-permission-appeal-against-building-sizewell-c

Continue ReadingCampaigners win permission to appeal against building of Sizewell C